Installation Instructions

1. Follow the Building Code

Be sure to follow the building code requirements applicable in your region.

2. First Layer of Insulation

Use nailers the same thickness as the first layer of insulation. Lay nailer, then insulation, then nailer up the slope of the roof, all joints tightly butted. Fasten nailer to deck as work proceeds.

3. Second Layer of Insulation

Lay second layer of insulation perpendicular to first layer. Lay insulation with joints tightly butted. Lay nailers over insulation spaced to support roof sheathing. Second layer of nailers to achieve a minimum airspace as determined by local building code.

4. Fastening Layers of Insulation

Fasten second layer nailer to first layer nailer where they intersect. If the thermal resistance requires extra layers of insulation, add layers to the bottom of the system changing the nailer direction as required. The top nailer must always run from the bottom of the roof slope to the ridge of roof.

5. Finish

Nail roof sheathing to nailers taking care that air movement is unobstructed in ventilation space.

6. Roofing Cover

Install roof covering in accordance with manufacturer's instructions. Adequate ventilation must be insured using an acceptable method to the applicable building code and/or local regulations.